← All standards & equipment
Fired Equipment

Shell-Type / Fire-Tube Boiler

Shell / fire-tube package boiler (low-medium pressure steam).

Category
Fired Equipment
Subcategory
Boiler
Applicable standards
4
Issuing bodies
4

Description

Shell / fire-tube package boiler (low-medium pressure steam).

Applicable Standards (4)

ASME — 1 standard

ASME BPVC Sec I Rules for Construction of Power Boilers
Edition: 2023 Edition Region: USA, Global
Power boilers, electric boilers, miniature boilers and HRSGs.
Key requirements (8)
  • Power boiler construction (steam generator) — section governs design, materials, fabrication.
  • Maximum allowable working pressure (MAWP) calculated per Section I formulas (PG-27 for tubes, PG-29 for shells).
  • Joint efficiency E: 1.0 (full RT), 0.85 (spot), 0.70 (no RT) for longitudinal seams.
  • Hydrostatic test: 1.5 × MAWP held minimum 30 minutes.
  • Mandatory PWHT and impact testing thresholds — stricter than VIII.
  • Watertube boiler MAWP often 100–200+ barg for utility; firetube to ~30 barg.
  • Material: SA-516, SA-285, SA-106, SA-335 (P11/P22/P91), etc.
  • Quality system / authorized inspection mandatory.

NFPA — 1 standard

NFPA 85 Boiler and Combustion Systems Hazards Code
Edition: 2023 Region: USA, Global
Combustion safeguards (BMS) for fuel-fired boilers and HRSGs.

EN/CEN — 1 standard

EN 12953 (series) Shell boilers
Edition: Various parts, 2002–2016 Region: Europe
Shell-and-tube (fire-tube) boilers.

Central Boilers Board (Govt. of India) — 1 standard

IBR 1950 Indian Boiler Regulations
Edition: 1950 (continuously amended) Region: India
Mandatory statutory regulation in India for boilers and steam piping >1.0 m³ volume or as defined by the IBR. Covers design, materials, fabrication, inspection, certification.
Key requirements (7)
  • Indian Boiler Regulations — statutory in India for any boiler > 25 L water capacity & > 1 kg/cm² g.
  • Approval/inspection by State Boiler Inspectorate (Chief Inspector of Boilers).
  • Materials: IBR-approved certified by IBR-approved test house only.
  • Hydrotest: 1.5 × design pressure after manufacture and at every annual inspection.
  • Annual inspection mandatory; certificate (Form VI) renewed yearly.
  • Welder qualification under IBR; approval valid for 2 years.
  • Boiler Manufacturer's Code (BMC) registration required.
Note: Statutory — applicable in addition to design codes for boilers and IBR-regulated steam piping in India.