ASME

ASME BPVC Sec I

Rules for Construction of Power Boilers

Issuing body
ASME
Latest edition
2023 Edition
Region
USA, Global
Equipment items
3

Scope

Power boilers, electric boilers, miniature boilers and HRSGs.

Key requirements (8)

  • Power boiler construction (steam generator) — section governs design, materials, fabrication.
  • Maximum allowable working pressure (MAWP) calculated per Section I formulas (PG-27 for tubes, PG-29 for shells).
  • Joint efficiency E: 1.0 (full RT), 0.85 (spot), 0.70 (no RT) for longitudinal seams.
  • Hydrostatic test: 1.5 × MAWP held minimum 30 minutes.
  • Mandatory PWHT and impact testing thresholds — stricter than VIII.
  • Watertube boiler MAWP often 100–200+ barg for utility; firetube to ~30 barg.
  • Material: SA-516, SA-285, SA-106, SA-335 (P11/P22/P91), etc.
  • Quality system / authorized inspection mandatory.